HighWay Projects
Four Laning of existing Thiruvananthapuram Bypass from Kazhakkoottam (Thiruvananthapuram) to Mukkola Junction from km 0.000 to km 26.500 under NHDP Phase IIIA in the State of Kerala on EPC Mode
Type of Project | EPC | SPV / Concessionaire | |||||
Client | National Highways Authority of India. | IE / AE | Yongma Engineering co. Ltd.,In association with Almondz Global Infra-consultant limited., | ||||
Contract Value in INR | 669.06 Cr | Completion Value in INR | 520.40 Cr | ||||
Commencement Date | 12-06-2015 | Completion Date (Original) | 11-06-2017 | ||||
Actual Start Date | 12-06-2015 | Revised Completion Date | 31-07-2018 | ||||
Highways | 2 Lane | 39.000 Kms | 4 Lane | 26.500 Kms | 6 Lane | ||
Express / 8 Lane | Total | 26.500 Kms | Service Road | 50.186 Kms | |||
Structures | Major Bridge | 3 Nos | Flyover | ROB | 2 Nos | ||
Minor Bridge | 8 Nos | Underpasses | 4 Nos | Culverts | 76 Nos |