Design, Construction, Development, Finance, Operation and Maintenance of Km 230/000 (Islam Nagar) to Km 278/000 (Kadtal) on NH-7 in the state of Andhra Pradesh under North – South Corridor (NHDP Phase II) on BOT (Annuity) Basis - Package No. NS-2/ BOT/ AP-07 KNR as Sub-contractor, Nirmal (Telangana) & Roads and Bridges.

EPC Contractor
M/s KNR Constructions Ltd
Our Share is
100%
Type of Project BOT (Annuity) SPV / Concessionaire Patel KNR Heavy infrastructure Pvt. Ltd.
Client National Highways Authority of India IE / AE M/s. ICT Consulting Pvt. Ltd
Contract Value in INR 503.00 Cr Completion Value in INR 503.00 Cr
Commencement Date 02-03-2008 Completion Date (Original) 01-03-2010
Actual Start Date 02-03-2008 Revised Completion Date 11-06-2010
Highways 2 Lane   4 Lane 48.000 Kms 6 Lane  
Express / 8 Lane   Total 48.000 Kms Service Road 3.900 Kms
Structures Major Bridge 2 Nos Flyover   ROB  
Minor Bridge 16 Nos Underpasses 18 Nos Culverts 95 Nos