Improvement/Augmentation of Four Laning from Km 5.000 to Km. 79.340 (Existing Chainage) [Design Chainage Km 5.000 to Km 81.000] and Two Laning with Paved Shoulders from Km 79.340 to Km 118.795 (Existing Chainage) [Design Chainage KM 81.000 to Km 120.000] of Madurai – Ramanathapuram section of NH-49 [Total Design Length 115.000 KM] in the State of Tamil Nadu under NHDP Phase-III on EPC MODE

Contractor
M/s KNR Constructions Ltd
Our Share is
100%
Type of Project EPC SPV / Concessionaire  
Client National Highways Authority of India. IE / AE Theme Engineering Services Pvt. Ltd.,
Contract Value in INR 937.08 Cr Completion Value in INR 756.36 Cr
Commencement Date 21-05-2015 Completion Date (Original) 20-11-2017
Actual Start Date 21-05-2015 Revised Completion Date 02-08-2018
Highways 2 Lane 39.000 Kms 4 Lane 76.000 Kms 6 Lane  
Express / 8 Lane   Total 115.000 Kms Service Road 12.840 Kms
Structures Major Bridge   Flyover   ROB 9 Nos
Minor Bridge 47 Nos Underpasses 2 Nos Culverts 191 Nos