Four Laning of Hubli - Hospet Section of NH-63 in the state of Karnataka on EPC Mode. Project Road Start from km 129.249 to km 267+000 on EPC Mode

JV Company
M/s BSC-KNR JV
Our Share in the JV is
50%
Type of Project EPC SPV / Concessionaire  
Client National Highways Authority of India. IE / AE Aarvee Associates
Contract Value in INR 1334.70 Cr Completion Value in INR 92.35 Cr
Commencement Date 15-03-2017 Completion Date (Original) 14-03-2020
Actual Start Date 15-03-2017 Revised Completion Date  
Highways 2 Lane   4 Lane 143.721 Kms 6 Lane  
Express / 8 Lane   Total 143.721 Kms Service Road 27.268 Kms
Structures Major Bridge 7 Nos Flyover 7 Nos ROB 1 Nos
Minor Bridge 47 Nos Underpasses 10 Nos Culverts 196 Nos