HighWay Projects
Construction of Major Bridge across River Godavari (Length 1.780 Kms) and its approaches (Length 18.690 Kms) at Eturunagaram on Hyderabad – Bhoopalapatnam Road of NH No. 163 (Old NH No. 202) including realignment in 1.960 Km length at 5 locations between Km 284/150 to 298/200-910 in the State of Andhra Pradesh under LWE Scheme
Type of Project | Item Rate | SPV / Concessionaire | |||||
Client | EE, R&B, NH Division, Eturunagaram | IE / AE | EE, R&B, NH Division, Eturunagaram | ||||
Contract Value in INR | 206.69 Cr | Completion Value in INR | 270.71 Cr | ||||
Commencement Date | 16-02-2012 | Completion Date (Original) | 15-03-2015 | ||||
Actual Start Date | 16-03-2012 | Revised Completion Date | 31-03-2016 |