HighWay Projects
Design, Construction, Development, Finance, Operation and Maintenance of Km 463.6 (AP/Karnataka border) to Km 524.0 (Avathi Village) and (ii) Improvement, Operation and Maintenance of Km 524 (Avathi Village) to Km 527 (Nandi Hills Crossing) and Km 535 (Devanhalli Village) to Km 539 (Meenukunte Village) on NH-7 in the State of Karnataka under North-South Corridor (NHDP Phase II) on BOT (Annuity) Basis - Package No. NS2/BOT/KNT-1, KNR as EPC Contractor, Chikballapur (Karnataka) & Roads and Bridges.
Type of Project | BOT (Annuity) | SPV / Concessionaire | Patel KNR infrastructures Pvt. Ltd. | ||||
Client | National Highways Authority of India | IE / AE | Aarvee Associates | ||||
Contract Value in INR | 350.00 Cr | Completion Value in INR | 403.36 Cr | ||||
Commencement Date | 27-03-2007 | Completion Date (Original) | 26-03-2009 | ||||
Actual Start Date | 27-03-2007 | Revised Completion Date | 21-12-2009 | ||||
Highways | 2 Lane | 4 Lane | 61.580 Kms | 6 Lane | |||
Express / 8 Lane | Total | 61.580 Kms | Service Road | 24.460 Kms | |||
Structures | Major Bridge | Flyover | 1 Nos | ROB | 3 Nos | ||
Minor Bridge | 20 Nos | Underpasses | 10 Nos | Culverts | 78 Nos |