HighWay Projects
Balance work of widening to 4/6 lanes and strengthening of existing 2-lane carriageway of NH-5 in the state of Orissa from Km. 284.000 to Km. 338.000 (Ganjam–Sunakhala), Construction Package OR-VII
Type of Project | Item Rate | SPV / Concessionaire | |||||
Client | National Highways Authority of India | IE / AE | Haskoning DHV Consulting Pvt Ltd | ||||
Contract Value in INR | 231.28 Cr | Completion Value in INR | 205.11 Cr | ||||
Commencement Date | 22-10-2009 | Completion Date (Original) | 21-10-2011 | ||||
Actual Start Date | 22-10-2009 | Revised Completion Date | 04-09-2013 |