HighWay Projects
Package NS - 32/TN - Balance works of Widening to 4-/6- lanes and Strengthening of Existing 2-lane Carriageway of NH-7 (Madurai – Kanniyakumari section) in the state of Tamil Nadu from Km 203.000 (of existing NH, Panagudy) to Km 234.690 (end point of proposed Kanniyakumari bypass)
Type of Project | Item Rate | SPV / Concessionaire | |||||
Client | National Highways Authority of India | IE / AE | Wilbur Smith Associates Pvt. Ltd | ||||
Contract Value in INR | 206.00 Cr | Completion Value in INR | 200.06 Cr | ||||
Commencement Date | 16-04-2008 | Completion Date (Original) | 15-04-2010 | ||||
Actual Start Date | 16-04-2008 | Revised Completion Date | 15-10-2010 |